2017-04-20, Demolition
- Demolition completed
- At the end of demo, found there was a water leak from ATCO, they were being called and the water valve was being fixed.
2017-04-22, Stake-out
- Survey did stake-out
- Fencing company installed theire fence
2017-04-24, Service in, Sewer service in
- The excavation company is doing the service tie-in
2017-04-29 – excavation down to 2′ more deeper
- the soil test did not pass, it has been decided 2′ deeper excavation is needed.
2017-05-01, Footing in
- Cribber has installed footing and waiting for it to be cured as well
2017-05-02, Cribbing
- The foundation wall is forming up
- The
2015-05-04, Curing
- Marked the Final Grade level (FG) and top of the floor (Slab) for the sump-pump liner
- Cribbing is curring for 6 days till May 8
- City footing and foundation inspection has been set on May 8
- Weeping tile sum-pump liner and the damp spray will be done by today and tomorrow.
- Electrician has installed the wire for the ground plate
2017-05-05, Weeping tile in
2017-05-08, city footing and foundation inspection passed
2017-05-10, Back fill
2017-05-11, Plumbing ground work
2017-05-12, Ground plumbing completion
2017-05-16, Framing starts
2017-05-18, Framing half-way through
2017-05-23, Main floor framing up
2017-05-31, basement slab preparation and truss to be on
2017-06-06, Hvac construction
2017-06-12, end stage of framing, middle of the Hvac
2017-06-16, roofing instruction